From NCDOT: The paving of East Oak Island Drive is scheduled to begin Monday morning, June 17, 2019. The work will start at the intersection of Country Club Drive and head west. Set up for traffic control will begin about 7 a.m. and the milling operation will start as soon as the traffic control is in place.

Traffic control will be accomplished using a flagging operation and a pilot car. Hopefully, local traffic will use the side streets where possible. We are anticipating that the impacts will be significant. We will be monitoring traffic throughout the day.

The Contractor is scheduled to work during the daylight hours Monday through Friday. They hope to complete the work in four (4) weeks. There is no work scheduled the entire week of July 4th. Work will shut down on Friday, June 28 and resume on Monday, July 8.