  • Progress on the dune restoration project

Progress on the dune restoration project

The Contractor working on the dune restoration project is currently working from the 55th Place East access, heading west at approximately 500 feet per day. We hope to complete between 55th and 52nd Wednesday and complete 52nd to 49th Friday. They will be working this Saturday in the area of Cabanas, heading west toward 46th, and should finish up to 46th by Tuesday of next week (April 25). They will open up the street accesses after they move away from them one at a time – the 58th East access should be opened by Wednesday (April 19). They will be placing foot traffic crossovers every 180 feet, like we had before. They will also be using post and rope to identify these crossovers. Planting of constructed dunes should start the last week in April. Please stay clear of the areas where crews are working – our shoreline is miles long so there are still plenty of open accesses. Thank you for your patience as we make these much-needed dune repairs!